top of page

COPL PROJECT

Crude Oil pipeline project of BPCL-Kochi refinery enabled the transfer of crude oil from shore tank farm facility of BPCL at  Puthuvypeen  to BPCL-Kochi refinery Ambalamugal. The first stage engineering and construction partner was M/s IVRCL and M/s NR Patel assisted to the second stage execution. Joining hands with M/s NR Patel we have executed the vital role of laying 8.65 Km 30” Cross Country Pipeline (piggable) from BPCL-KR, Ambalamugal to Ernakulam South, terminal pipelines and erection of equipment at STF Puthuvypeen. The total project had an executed value of 6.45 Cr.